"/>

国产一级片一区二区三区Iav黄色免费看I久久久久国产成人免费精品免费I人成午夜视频I97福利在线I国产麻豆剧传媒免费观看I久久爱www.I一区二区三区视频在线I久久免费高清I麻豆国产精品永久免费视频I91尤物国产尤物福利在线播放

Spotlight: Seven years on, Fukushima nuclear cleanup still long way to go
Source: Xinhua   2018-03-11 20:29:28

TOKYO, March 11 (Xinhua) -- Seven years after one of the worst nuclear disasters in history, Japan is still struggling with the aftermaths, not only the tough tasks of reconstruction, but also nuclear cleanup work that is expected to take generations, with hefty costs and unsolved technical problems.

The massive earthquake and the ensuing tsunami on March 11, 2011 severely damaged three reactors at Daiichi facility in Fukushima, which suffered core meltdowns after their key cooling systems were knocked out and backup power supplies rendered useless.

Tokyo Electric Power Company Holdings Inc. (TEPCO), operator of the crippled Fukushima Daiichi nuclear plant, had since successfully decommissioned the No. 5 and 6 reactors at the plant, and more than 1,500 fuel rods in the No. 4 reactor had been taken out and safely stored by the end of 2014.

But the problem lies with removing the melted nuclear fuel and debris from the No.1 to 3 reactors, which, according to experts, poses the biggest challenge to the decommission work.

The Japanese government and TEPCO have made plans to start fuel removal from the three reactors in 2021, but experts have expressed doubts regarding whether the plan could be carried out as scheduled.

Toyoshi Fuketa, Nuclear Regulation Authority Chairman, told a press conference recently that the removal work has not yet reached a point where "exit is in sight."

One of the difficulties lies in the extremely high radiation levels inside the reactors.

TEPCO said last month that levels of radiation detected inside the No. 2 reactor in a January probe were as high as 7-42 sieverts per hour, still enough to kill a person for just a short period of exposure.

The operator of the crippled plant, having established the path of conducting the cleanup work through remote mechanic systems, is still struggling with finding more viable technical solutions to the process.

The whole process also comes with a hefty price tag. According to Japan's Ministry of Economy, Trade and Industry, the cost of the decontamination work and treatment of polluted water, is expected to surge to 8 trillion yen (75 billion U.S. dollars) in total.

The number was much higher according to the calculation of a civil group Atomic Energy Citizens' Committee, reaching roughly 30 trillion yen (281 billion U.S. dollars).

Other thorny problems include decontaminating the soil and treating the contaminated water.

To keep the No.1 to 3 reactors cooled, TEPCO has to inject a large amount of fresh water into the reactors constantly. The water becomes radioactive in the process and is then stored in the basement of the reactor buildings. TEPCO's "decontamination" facilities can remove radioactive cesium and strontium from the water but not tritium.

TEPCO released a limited amount of radioactive water into the Pacific Ocean after getting approval from the local fishery association in September 2015. But there is not enough scientific research to determine that dumping contaminated water into the ocean is safe.

Some much-vaunted measures turned out not as efficient as they were originally planned while costing a huge sum of the money.

A government-commissioned group of experts concluded recently that a costly underground ice wall is only partially effective in reducing the ever-growing amount of contaminated water at the nuclear plant.

The wall cost 34.5 billion yen (323 million U.S. dollars) to build and is expected to cost more than 1 billion yen (9.4 million U.S. dollars) annually in operating and maintenance.

Most of the hefty expenses would have to be borne by taxpayers, as TEPCO, which was bailed out by the government, has been grappling with difficult financial situations when coping with the lengthy task of decommissioning the plant and carrying out cleanup work which is likely to take decades.

The operator of the Fukushima Daiichi nuclear plant has also been hit with a number of lawsuits for alleged negligence or improper design, construction and maintenance of the nuclear facilities.

"The multiple disasters that struck Fukushima seven years ago are not something that just belongs to the past, but are still affecting us," said Fukushima Governor Masao Uchibori.

Editor: Chengcheng
Related News
Xinhuanet

Spotlight: Seven years on, Fukushima nuclear cleanup still long way to go

Source: Xinhua 2018-03-11 20:29:28
[Editor: huaxia]

TOKYO, March 11 (Xinhua) -- Seven years after one of the worst nuclear disasters in history, Japan is still struggling with the aftermaths, not only the tough tasks of reconstruction, but also nuclear cleanup work that is expected to take generations, with hefty costs and unsolved technical problems.

The massive earthquake and the ensuing tsunami on March 11, 2011 severely damaged three reactors at Daiichi facility in Fukushima, which suffered core meltdowns after their key cooling systems were knocked out and backup power supplies rendered useless.

Tokyo Electric Power Company Holdings Inc. (TEPCO), operator of the crippled Fukushima Daiichi nuclear plant, had since successfully decommissioned the No. 5 and 6 reactors at the plant, and more than 1,500 fuel rods in the No. 4 reactor had been taken out and safely stored by the end of 2014.

But the problem lies with removing the melted nuclear fuel and debris from the No.1 to 3 reactors, which, according to experts, poses the biggest challenge to the decommission work.

The Japanese government and TEPCO have made plans to start fuel removal from the three reactors in 2021, but experts have expressed doubts regarding whether the plan could be carried out as scheduled.

Toyoshi Fuketa, Nuclear Regulation Authority Chairman, told a press conference recently that the removal work has not yet reached a point where "exit is in sight."

One of the difficulties lies in the extremely high radiation levels inside the reactors.

TEPCO said last month that levels of radiation detected inside the No. 2 reactor in a January probe were as high as 7-42 sieverts per hour, still enough to kill a person for just a short period of exposure.

The operator of the crippled plant, having established the path of conducting the cleanup work through remote mechanic systems, is still struggling with finding more viable technical solutions to the process.

The whole process also comes with a hefty price tag. According to Japan's Ministry of Economy, Trade and Industry, the cost of the decontamination work and treatment of polluted water, is expected to surge to 8 trillion yen (75 billion U.S. dollars) in total.

The number was much higher according to the calculation of a civil group Atomic Energy Citizens' Committee, reaching roughly 30 trillion yen (281 billion U.S. dollars).

Other thorny problems include decontaminating the soil and treating the contaminated water.

To keep the No.1 to 3 reactors cooled, TEPCO has to inject a large amount of fresh water into the reactors constantly. The water becomes radioactive in the process and is then stored in the basement of the reactor buildings. TEPCO's "decontamination" facilities can remove radioactive cesium and strontium from the water but not tritium.

TEPCO released a limited amount of radioactive water into the Pacific Ocean after getting approval from the local fishery association in September 2015. But there is not enough scientific research to determine that dumping contaminated water into the ocean is safe.

Some much-vaunted measures turned out not as efficient as they were originally planned while costing a huge sum of the money.

A government-commissioned group of experts concluded recently that a costly underground ice wall is only partially effective in reducing the ever-growing amount of contaminated water at the nuclear plant.

The wall cost 34.5 billion yen (323 million U.S. dollars) to build and is expected to cost more than 1 billion yen (9.4 million U.S. dollars) annually in operating and maintenance.

Most of the hefty expenses would have to be borne by taxpayers, as TEPCO, which was bailed out by the government, has been grappling with difficult financial situations when coping with the lengthy task of decommissioning the plant and carrying out cleanup work which is likely to take decades.

The operator of the Fukushima Daiichi nuclear plant has also been hit with a number of lawsuits for alleged negligence or improper design, construction and maintenance of the nuclear facilities.

"The multiple disasters that struck Fukushima seven years ago are not something that just belongs to the past, but are still affecting us," said Fukushima Governor Masao Uchibori.

[Editor: huaxia]
010020070750000000000000011100001370320231
主站蜘蛛池模板: 欧美z0zo人禽交免费观看99| 日韩成人极品在线内射3p蜜臀| 国产亚洲精品久久久久久小说| 无码手机线免费播放三区视频| 人妻少妇伦在线无码专区视频| 日本熟妇浓毛| 中国肥老太婆高清video| 国产深夜男女无套内射| 免费看婬乱a欧美大片| 亚洲国产精品无码中文字满| 色婷婷在线精品国自产拍| 久久日本片精品aaaaa国产| 人妻有码精品视频在线| 狠狠躁天天躁中文字幕无码| 欧美日本免费一区二区三区| 亚洲无码不卡| 奇米影视7777狠狠狠狠色| 亚洲人成在久久综合网站 | 综合久久—本道中文字幕| 成在人线av无码免费高潮水| 久久综合精品国产二区无码| 亚洲精品卡2卡3卡4卡5卡区| 久久精品国产久精国产爱| 狠痕鲁狠狠爱2021在| 欧美极品色午夜在线视频| 一二三四在线观看视频韩国| 日韩一区二区三区无码a片| 欧美日韩综合精品一区二区| 国产涩涩视频在线观看| 日本三级片在线| 亚洲自偷自拍熟女另类| 99精品久久久久久久婷婷| 欧美激情乱人伦| 欧洲精品码一区二区三区免费看| 欧美交换配乱吟粗大| 精品无码久久久久久久久| 国产精品亚洲精品日韩动图| 爆乳高潮喷水无码正在播放 | 久久人妻精品白浆国产| 中文字幕有码无码人妻在线| 国产妇女馒头高清泬20p多|