国产一级片一区二区三区Iav黄色免费看I久久久久国产成人免费精品免费I人成午夜视频I97福利在线I国产麻豆剧传媒免费观看I久久爱www.I一区二区三区视频在线I久久免费高清I麻豆国产精品永久免费视频I91尤物国产尤物福利在线播放

 
Feature: Uganda's new hydropower plant set to relieve power shortage, bridge skills transfer
                 Source: Xinhua | 2019-01-05 20:08:24 | Editor: huaxia

Chinese and Ugandan technicians work at the construction site of Isimba Power Plant Project in Kayunga district, Uganda, Aug. 8, 2017. As River Nile, the longest in the world, snakes through central Uganda, Chinese engineers and their local counterparts are constructing a multi-million U.S. dollar power plant on its bank in the remote Kayunga district. (Xinhua/Zhang Gaiping)

by Ronald Ssekandi, Zhang Gaiping

KAYUNGA, Uganda, Jan. 5 (Xinhua) -- Inside the power house at Isimba Hydropower Plant in the central Ugandan district of Kayunga, engineers subject the first unit of the plant to tests before the official commissioning slated for late January.

The engineers told Xinhua in a recent interview that after the commissioning of the first unit, they will move onto the second, third and eventually the fourth.

RELIEVING POWER SHORTAGE

The four units of the 183 MW Chinese constructed power plant would be commissioned in a phased manner, according to Xia Nenghai, General Manager of Uganda Branch, China International Water and Electric Corporation (CWE). CWE is the EPC contractor of the project.

Outside the power house, local workers under the supervision of Chinese technicians put final touches on the structural works.

"The civil work, the embankment of the dam, and the power house construction, the installation of the electric, mechanical equipment have been fully completed," said Xia.

The construction of the 568 million U.S. dollars power plant located on River Nile, the world's longest River, started in 2015, after Uganda secured a loan from China Export Import Bank. Uganda got the loan to address the country's power shortage, which economic experts said was stalling economic development.

After commissioning of all the units, the plant will generate the installed capacity of 183 MW, which is currently about 19 percent of the country's power generated. The country generates up to 974.84 MW, which experts say is inadequate and expensive.

When the Isimba power comes on to the national grid, it is expected to partly address the shortfall, according to the government.

Another Chinese funded Karuma Hydropower Plant is being constructed and is expected to generate 600 MW. The government anticipates that both the Isimba and Karuma power will address the country's power shortage.

SKILLS TRANSFER

At the construction site, the workforce has reduced as most of the structural works have been completed. What is now remaining is largely electrical and mechanical works, according to Xia.

At the peak of the construction, there were over 3,000 local workers ranging from semi-skilled to skilled.

Most of the youths who worked at the site gained more skills that they would use even after the project is long completed, according to Xia.

He said although the power plant is Chinese constructed, it has an American design as requested by the Ugandan government.

"We want to bring our Chinese knowledge, skills and management to the Ugandan people so that they can have more capability to work for their nation in future because we cannot stay here forever," Xia said.

"In future, Ugandans will build their country by themselves, with the correct skills," he added.

In communities neighboring the construction site, there is noticeable change as what was a small trading center has now expanded. Some of the workers from different parts of the country reside in the Busana trading center.

Xia said most of the employees were recruited from the community and surrounding districts, which explains the development in the area.

CWE also renovated a nearby school, Nakakandwa Primary School. The company, as part of its corporate social responsibility gave a new face-lift to the school.

Back to Top Close
Xinhuanet

Feature: Uganda's new hydropower plant set to relieve power shortage, bridge skills transfer

Source: Xinhua 2019-01-05 20:08:24

Chinese and Ugandan technicians work at the construction site of Isimba Power Plant Project in Kayunga district, Uganda, Aug. 8, 2017. As River Nile, the longest in the world, snakes through central Uganda, Chinese engineers and their local counterparts are constructing a multi-million U.S. dollar power plant on its bank in the remote Kayunga district. (Xinhua/Zhang Gaiping)

by Ronald Ssekandi, Zhang Gaiping

KAYUNGA, Uganda, Jan. 5 (Xinhua) -- Inside the power house at Isimba Hydropower Plant in the central Ugandan district of Kayunga, engineers subject the first unit of the plant to tests before the official commissioning slated for late January.

The engineers told Xinhua in a recent interview that after the commissioning of the first unit, they will move onto the second, third and eventually the fourth.

RELIEVING POWER SHORTAGE

The four units of the 183 MW Chinese constructed power plant would be commissioned in a phased manner, according to Xia Nenghai, General Manager of Uganda Branch, China International Water and Electric Corporation (CWE). CWE is the EPC contractor of the project.

Outside the power house, local workers under the supervision of Chinese technicians put final touches on the structural works.

"The civil work, the embankment of the dam, and the power house construction, the installation of the electric, mechanical equipment have been fully completed," said Xia.

The construction of the 568 million U.S. dollars power plant located on River Nile, the world's longest River, started in 2015, after Uganda secured a loan from China Export Import Bank. Uganda got the loan to address the country's power shortage, which economic experts said was stalling economic development.

After commissioning of all the units, the plant will generate the installed capacity of 183 MW, which is currently about 19 percent of the country's power generated. The country generates up to 974.84 MW, which experts say is inadequate and expensive.

When the Isimba power comes on to the national grid, it is expected to partly address the shortfall, according to the government.

Another Chinese funded Karuma Hydropower Plant is being constructed and is expected to generate 600 MW. The government anticipates that both the Isimba and Karuma power will address the country's power shortage.

SKILLS TRANSFER

At the construction site, the workforce has reduced as most of the structural works have been completed. What is now remaining is largely electrical and mechanical works, according to Xia.

At the peak of the construction, there were over 3,000 local workers ranging from semi-skilled to skilled.

Most of the youths who worked at the site gained more skills that they would use even after the project is long completed, according to Xia.

He said although the power plant is Chinese constructed, it has an American design as requested by the Ugandan government.

"We want to bring our Chinese knowledge, skills and management to the Ugandan people so that they can have more capability to work for their nation in future because we cannot stay here forever," Xia said.

"In future, Ugandans will build their country by themselves, with the correct skills," he added.

In communities neighboring the construction site, there is noticeable change as what was a small trading center has now expanded. Some of the workers from different parts of the country reside in the Busana trading center.

Xia said most of the employees were recruited from the community and surrounding districts, which explains the development in the area.

CWE also renovated a nearby school, Nakakandwa Primary School. The company, as part of its corporate social responsibility gave a new face-lift to the school.

010020070750000000000000011100001377220451
主站蜘蛛池模板: 亚洲 日韩 欧美 有码 在线| 动漫成人无码精品一区二区三区| 日产中文字幕在线观看| 国产色在线 | 日韩| 国产suv精品一区二区四| 久久久免费无码成人影片| 久久天堂综合亚洲伊人hd妓女 | 日本做受高潮好舒服视频| 国产在线精品成人一区二区| 国产揉捏爆乳巨胸挤奶视频| 日韩久久无码精品不卡一区二区电影| xxxxx欧美| 一本到在线观看视频| 琪琪777午夜理论片在线观看播放| 人妻av无码中文专区久久| 国产精品99久久不卡| 欧美精品a∨在线观看| 18精品久久久无码午夜福利| 色吊丝永久性观看网站| 成人免费无码大片a毛片| 熟女少妇人妻中文字幕| 伊人色合天天久久综合网| 日本19禁啪啪吃奶大尺度| 丰满肥臀大屁股熟妇激情视频| 久久理论片午夜琪琪电影网| 色窝窝免费播放视频在线| 久久久久国产精品| 久久99久久99精品免视看| 亚洲a片无码一区二区蜜桃| 国产亚洲精品在av| 国产午夜福利精品久久2021| 久久精品中文字幕有码| 免费无码成人av片在线在线播放| av狠狠色超碰丁香婷婷综合久久| 国产亚洲精品bt天堂精选| 久久久欧美国产精品人妻| 亚洲国产精品嫩草影院| 裸体美女无遮挡免费网站 | 在线观看午夜亚洲一区| 久久久久久久久888| 亚洲精品色情aⅴ色戒|